Question 6 of 12
A can do a job in 15 days and B in 20 days. They work together for 4 days, then A leaves. How many more days will B need to finish the rest?
- A 11 days
- B 10 2/3 days
- C 9 days
- D 8 days
B. 10 2/3 days
Step 1: together per day = 1/15 + 1/20 = 7/60
→ Step 2: work in 4 days = 28/60 = 7/15
→ Step 3: remaining = 8/15
→ Step 4: B's rate = 1/20
→ Step 5: time = (8/15) ÷ (1/20) = 32/3 = 10 2/3 days
→ Answer: 10 2/3 days