P can finish a task in 6 days and Q in 9 days. P works alone for 2 days, then Q joins him. How many more days do they need together to finish?
- A 2 days
- B 3 days
- C 2.4 days
- D 2 1/2 days
C. 2.4 days
Step 1: P's work in 2 days = 2/6 = 1/3
→ Step 2: remaining = 2/3
→ Step 3: together per day = 1/6 + 1/9 = 5/18
→ Step 4: time = (2/3) ÷ (5/18) = 12/5 = 2.4 days
→ Answer: 2.4 days